title: Semi-Permanent Loading Warehouses
date: 2025-05-19T15:40:00+01:00
author: Tabitha Loose
canonical_url: "https://www.spaciotempo.co.uk/case-studies/mm-freight"
section: Case Studies
---
![Dji fly 20230131 125840 417 1675170639965 aeb optimized](/uploads/generic/previews/_1920x1280_crop_center-center_none/dji_fly_20230131_125840_417_1675170639965_aeb_optimized.jpg)  

 

  

 

 

MM Freight

# Semi-Permanent Loading Warehouses

 

 

 

    Loading Building 

  Building 1: 414m² Building 2: 825m² 

  Lurgan, Northern Ireland 

 ![line drawing of a building and a circle on top](/uploads/generic/Product-Icons/neivalu.svg) Neivalu 

 

    ## Loading &amp; Unloading Warehouses

MM Freight partnered with Spaciotempo to deliver two bespoke modular buildings at their Craigavon depot. Originally seeking a fast and cost-effective solution to support growing chilled goods operations, the success of the initial structure led to a second, larger building being commissioned both now forming an essential part of their permanent infrastructure.

 

   ![Mm freight ltd lurgan logo](/uploads/generic/_AUTOx100_crop_center-center_none/mm_freight_ltd_lurgan_logo.jpg)  

 

 

 

 

         ![IMG 4971 1](/uploads/generic/_2800x2000_crop_center-center_none/17843/IMG_4971-1.jpg)  

  ## Requirements

 

As a leading temperature-controlled logistics provider with operations across the UK and Ireland, MM Freight needed to expand chilled distribution capacity at their Northern Ireland depot. They required a fast-turnaround solution that could accommodate high volumes of cross-docking activity, while maintaining temperature control and allowing safe, efficient vehicle loading in all weather conditions.

To support this, they were looking for a partner who could deliver everything in-house from initial design through to installation with minimal disruption to operations.

 

 

 

 

 

         ![IMG 4972](/uploads/generic/_600x600_crop_center-center_none/17846/IMG_4972.jpg)  

 

 

       ![IMG 4951](/uploads/generic/_600x600_crop_center-center_none/17849/IMG_4951.jpg)  

 

 

       ![Dji fly 20230131 130010 432 1675170620545 aeb optimized](/uploads/generic/_600x600_crop_center-center_none/dji_fly_20230131_130010_432_1675170620545_aeb_optimized.jpg)  

 

 

 

 

 

 

  Previous   MM Freight’s Craigavon depot, featuring the two modular structures with integrated canopies and dock doors.

 

 Interior of the chilled cross-docking facility, designed for efficient and weather-protected goods handling.

 

 Aerial view showing the scale and layout of both permanent modular buildings and the insulated link tunnel.

 

 

 

  Next   

 

 

 

  ## The solution

 

Spaciotempo delivered two purpose-built modular structures for MM Freight, both tailored to meet the operational needs of their Craigavon depot. The first structure provided an immediate uplift in chilled cross-docking capacity, while the success of this installation led to the commissioning of a second, larger facility — further increasing throughput and long-term site capability.

 

 

(01)

### Phase 1: 414m² Temporary Warehouse

         ![IMG 4971 1](/uploads/generic/_1246x625_crop_center-center_none/17854/IMG_4971-1_2025-05-19-113033_sydl.jpg)  

 

The initial 414m² building was installed in just one week and included a 1.5m canopy extension and integrated dock leveller, enabling weather-protected loading and safe, efficient movement of goods. Designed to operate as a chilled distribution hub, the structure was quickly integrated into MM Freight’s daily workflow and became a vital component of their site operations.

 

 

 

 ![Decorative blurred photo](/dist/images/cs-details-blur-lg.png) 

(02)

### Phase 2: Expansion Through a Second, Larger Structure

         ![IMG 4951](/uploads/generic/_1246x625_crop_center-center_none/17849/IMG_4951.jpg)  

 

Following the smooth delivery and strong performance of the first building, MM Freight commissioned a second 825m² facility to expand their capabilities even further. This larger structure included multiple dock doors, a thermo-insulated blackout roof, and a covered mini canopy to maintain year-round protection. An 8m-wide insulated tunnel was installed to connect both buildings, allowing seamless internal movement between the two units and supporting high-volume, chilled logistics on site.

 

 

 

 

(03)

### Outcome

Spaciotempo completed both builds on time, on budget and to specification, enabling MM Freight to scale their logistics infrastructure without disruption.

Today, the two modular structures are a permanent fixture of MM Freight’s operations in Craigavon, supporting a chilled cross-docking and distribution system that plays a key role in their national supply chain.

Thanks to Spaciotempo’s single-provider model, MM Freight benefitted from:

\- Fully customised, operationally aligned solutions

\- Rapid deployment across both builds

\- Seamless integration between new and existing infrastructure

\- Scalable structures that support long-term growth objectives

 

 

 

 ![Decorative blurred photo](/dist/images/cs-details-blur-sm.png) 

 

 

  ## Temporary buildings.   
Lasting solutions.

Be it lack of storage or warehouse space, production or maintenance facilities, or cover for your loading and unloading operations, our structures meet every requirement.

 

 

 

 [Industrial brochure

  PDF download 

 

 ](https://www.spaciotempo.co.uk/brochures/temporary-buildings-lasting-solutions-brochure) [Get a quote

  Online form 

 

 ](https://www.spaciotempo.co.uk/get-a-quote) 

 

 

  

 [ Go to Farrell Transport - Permanent Canopy Solution case study ](https://www.spaciotempo.co.uk/case-studies/farrell-transport)           ![Permanent Loading Canopy at Farrall Transport](/uploads/generic/previews/Case-Study-Preview-images/_1920x1280_crop_center-center_none/Permanent-Loading-Canopy-at-Farrall-Transport.jpg)  

 

Farrell Transport

## Permanent Canopy Solution

Next   
Project

 

 

 

 ### Kickstart your build today.

Don’t let space limitations hold back your business growth. Start your project now!

 [ Get a quote   

 ](https://www.spaciotempo.co.uk/get-a-quote) 

### Temporary buildings brochure

Our brochure places a firm focus on your industry. Download for an insight into our capability and to view past examples of projects we’ve delivered.

 [  Download brochure ](https://www.spaciotempo.co.uk/brochures/company-brochure) 

 

### Temporary buildings FAQs

Understand everything there is to know about temporary buildings, from planning requirements to aftercare.

 [  FAQs ](https://www.spaciotempo.co.uk/faqs) 

 

 

 

 

 

 

  &lt;![CDATA[YII-BLOCK-BODY-END]]&gt;